Dynamic memory-aware task-tree scheduling
Résumé
Factorizing sparse matrices using direct multifrontal methods generates
directed tree-shaped task graphs, where edges represent data
dependency between tasks. This paper revisits the execution of
tree-shaped task graphs using multiple processors that share a
bounded memory. A task can only be executed if all its input and
output data can fit into the memory. The key difficulty is to manage
the order of the task executions so that we can achieve
high parallelism while staying below the memory bound. In
particular, because input data of unprocessed tasks must be kept
in memory, a bad scheduling strategy might compromise the
termination of the algorithm. In the single processor case,
solutions that are guaranteed to be below a memory bound are
known. The multi-processor case (when one tries to minimize the
total completion time) has been shown to be NP-complete. We present in
this paper a novel heuristic solution that has a low complexity and
is guaranteed to complete the tree within a given memory bound. We
compare our algorithm to state of the art strategies, and observe
that on both actual execution trees and synthetic trees, we
always perform better than these solutions, with average speedups
between 1.25 and 1.45 on actual assembly trees.
Moreover, we show that the overhead of our algorithm is negligible even on
deep trees (10^5), and would allow its runtime
execution.